Task templatesCeilings and partitions
SW

Ceilings and partitions

Metal stud partitions, fire stopping and suspended ceilings.

Ceilings & partitions4 tasks2 hold pointsUsed by 0 packages:
1

No dependency — can start at mobilisation

Progress

100%

Checklist

  • Head deflection detail correct
  • Studs at specified centres
  • Openings framed

Photo evidence

  • Stud line before boarding3 required
2

Starts after: Stud partitions

Progress

60%

Checklist

  • Every penetration sealed
  • Products within their tested scope
  • Fire stopping register updated

Photo evidence

  • Each sealed penetration4 required

Work cannot be covered up until this hold point is inspected and accepted.

3

Starts after: Fire stopping

Progress

35%

Checklist

  • Grid level within 3 mm over 5 m
  • Perimeter cuts even
  • Tiles clean and unmarked

Photo evidence

  • Grid and tiles2 required
4

Starts after: Ceiling grid and tiles

Progress

0%

Checklist

  • Services accessible
  • Void clear of debris
  • Sign-off sheet complete

Photo evidence

  • Void before closing3 required

Work cannot be covered up until this hold point is inspected and accepted.