Task templatesElectrical fit-out
SW

Electrical fit-out

Containment through to final certification for a standard Jersey Mike's unit.

Electrical first & second fix5 tasks2 hold pointsUsed by 3 packages: JM008, JM024, JM051
1

No dependency — can start at mobilisation

Progress

100%

Checklist

  • Tray route matches the coordinated services drawing
  • Fixings at maximum 1.2 m centres
  • Earth bonding continuous across joints

Photo evidence

  • Completed tray run, both directions2 required
2

Starts after: Containment and cable tray

Progress

100%

Checklist

  • Cables labelled at both ends
  • Segregation from data maintained
  • Cable schedule updated

Photo evidence

  • Cable drops at each counter position4 required
3

Starts after: First fix wiring

Progress

80%

Checklist

  • Board fixed level and accessible
  • Circuit chart printed and fitted
  • Torque settings recorded

Photo evidence

  • Board internals before cover fitted2 required
  • Circuit chart1 required

Work cannot be covered up until this hold point is inspected and accepted.

4

Starts after: Distribution board install

Progress

55%

Checklist

  • All plates fitted square
  • No damage to finishes
  • Faceplate colours match specification

Photo evidence

  • Each till position3 required
5

Starts after: Second fix accessories

Progress

0%

Checklist

  • Insulation resistance recorded
  • RCD trip times within limits
  • EIC issued and uploaded

Photo evidence

  • Test instrument readout2 required

Work cannot be covered up until this hold point is inspected and accepted.