Task templatesElectrical fit-out
SW
Electrical fit-out
Containment through to final certification for a standard Jersey Mike's unit.
Electrical first & second fix5 tasks2 hold pointsUsed by 3 packages: JM008, JM024, JM051
1
No dependency — can start at mobilisation
Progress
100%
Checklist
- Tray route matches the coordinated services drawing
- Fixings at maximum 1.2 m centres
- Earth bonding continuous across joints
Photo evidence
- Completed tray run, both directions2 required
2
Starts after: Containment and cable tray
Progress
100%
Checklist
- Cables labelled at both ends
- Segregation from data maintained
- Cable schedule updated
Photo evidence
- Cable drops at each counter position4 required
3
Starts after: First fix wiring
Progress
80%
Checklist
- Board fixed level and accessible
- Circuit chart printed and fitted
- Torque settings recorded
Photo evidence
- Board internals before cover fitted2 required
- Circuit chart1 required
Work cannot be covered up until this hold point is inspected and accepted.
4
Starts after: Distribution board install
Progress
55%
Checklist
- All plates fitted square
- No damage to finishes
- Faceplate colours match specification
Photo evidence
- Each till position3 required
5
Starts after: Second fix accessories
Progress
0%
Checklist
- Insulation resistance recorded
- RCD trip times within limits
- EIC issued and uploaded
Photo evidence
- Test instrument readout2 required
Work cannot be covered up until this hold point is inspected and accepted.