Task templatesFloor and wall finishes
SW
Floor and wall finishes
Resin kitchen floor, front-of-house tiling and wall finishes.
Floor finishes4 tasks1 hold pointsUsed by 0 packages:
1
No dependency — can start at mobilisation
Progress
100%
Checklist
- Moisture reading recorded
- Surface ground and vacuumed
- Primer applied within the open time
Photo evidence
- Moisture meter reading2 required
Work cannot be covered up until this hold point is inspected and accepted.
2
Starts after: Substrate preparation
Progress
80%
Checklist
- Coving formed to 150 mm
- Falls to gully verified
- Batch numbers recorded
Photo evidence
- Coving detail3 required
3
Starts after: Resin kitchen floor
Progress
40%
Checklist
- Tile layout matches the setting-out plan
- Grout colour approved
- Movement joints at thresholds
Photo evidence
- Tiled area3 required
4
Starts after: Front-of-house tiling
Progress
0%
Checklist
- Protection boards laid
- Cleaning regime issued
- Warranty documents uploaded
Photo evidence
- Protected floor1 required