Task templatesHandover and commissioning
SW

Handover and commissioning

Final commissioning, training and the store handover pack.

Handover pack4 tasks2 hold pointsUsed by 0 packages:
1

No dependency — can start at mobilisation

Progress

90%

Checklist

  • Fire alarm interfaces proven
  • Extract shutdown proven
  • Results logged

Photo evidence

  • Alarm panel during test2 required

Work cannot be covered up until this hold point is inspected and accepted.

2

Starts after: Integrated systems test

Progress

60%

Checklist

  • Attendee list signed
  • Equipment demonstrations recorded
  • Quick reference cards left on site

Photo evidence

  • Training session1 required
3

Starts after: Store team training

Progress

40%

Checklist

  • All sections indexed
  • Test certificates included
  • As-built drawings issued

Photo evidence

  • Contents page1 required
4

Starts after: O&M and H&S file upload

Progress

0%

Checklist

  • Snag list agreed
  • Keys and access cards handed over
  • Acceptance certificate signed

Photo evidence

  • Completed store, front of house3 required

Work cannot be covered up until this hold point is inspected and accepted.