Task templatesHandover and commissioning
SW
Handover and commissioning
Final commissioning, training and the store handover pack.
Handover pack4 tasks2 hold pointsUsed by 0 packages:
1
No dependency — can start at mobilisation
Progress
90%
Checklist
- Fire alarm interfaces proven
- Extract shutdown proven
- Results logged
Photo evidence
- Alarm panel during test2 required
Work cannot be covered up until this hold point is inspected and accepted.
2
Starts after: Integrated systems test
Progress
60%
Checklist
- Attendee list signed
- Equipment demonstrations recorded
- Quick reference cards left on site
Photo evidence
- Training session1 required
3
Starts after: Store team training
Progress
40%
Checklist
- All sections indexed
- Test certificates included
- As-built drawings issued
Photo evidence
- Contents page1 required
4
Starts after: O&M and H&S file upload
Progress
0%
Checklist
- Snag list agreed
- Keys and access cards handed over
- Acceptance certificate signed
Photo evidence
- Completed store, front of house3 required
Work cannot be covered up until this hold point is inspected and accepted.