Task templatesMechanical services
SW
Mechanical services
Ventilation, kitchen extract and heating for a trading kitchen.
Mechanical services4 tasks2 hold pointsUsed by 3 packages: JM024, JM024, JM042
1
No dependency — can start at mobilisation
Progress
100%
Checklist
- Duct supported to DW144
- Fire dampers positioned per drawing
- Access panels reachable
Photo evidence
- Duct run above ceiling line3 required
2
Starts after: Ductwork first fix
Progress
90%
Checklist
- Canopy level and sealed to wall
- Grease filters fitted
- Make-up air balanced
Photo evidence
- Canopy in place2 required
3
Starts after: Kitchen extract canopy
Progress
45%
Checklist
- Each damper released and reset
- Test certificate issued
- Damper tags legible
Photo evidence
- Each damper tag4 required
Work cannot be covered up until this hold point is inspected and accepted.
4
Starts after: Fire damper drop test
Progress
0%
Checklist
- Air volumes within 10% of design
- Commissioning sheets signed
- Noise levels recorded in the seating area
Photo evidence
- Anemometer reading at each grille4 required
Work cannot be covered up until this hold point is inspected and accepted.