Task templatesRefrigeration and cold room
SW
Refrigeration and cold room
Cold room build, pipework and temperature validation.
Walk-in cold room4 tasks2 hold pointsUsed by 2 packages: JM019, JM042
1
No dependency — can start at mobilisation
Progress
100%
Checklist
- Panels locked and plumb
- Floor junction sealed food-safe
- Door closes and seals
Photo evidence
- Internal corners3 required
2
Starts after: Panel build and floor seal
Progress
70%
Checklist
- Nitrogen test held for 24 hours
- Pressure log attached
- Insulation continuous
Photo evidence
- Pressure gauge at start and end2 required
Work cannot be covered up until this hold point is inspected and accepted.
3
Starts after: Pipework and pressure test
Progress
40%
Checklist
- High-temperature alarm tested
- Door alarm tested
- Setpoints match the brand standard
Photo evidence
- Controller display1 required
4
Starts after: Controls and alarms
Progress
0%
Checklist
- Data logger downloaded
- Pull-down time within specification
- Validation report uploaded
Photo evidence
- Logger graph1 required
Work cannot be covered up until this hold point is inspected and accepted.