Refrigeration and cold room

Cold room build, pipework and temperature validation.

Walk-in cold room4 tasks2 hold pointsUsed by 2 packages: JM019, JM042
1

No dependency — can start at mobilisation

Progress

100%

Checklist

  • Panels locked and plumb
  • Floor junction sealed food-safe
  • Door closes and seals

Photo evidence

  • Internal corners3 required
2

Starts after: Panel build and floor seal

Progress

70%

Checklist

  • Nitrogen test held for 24 hours
  • Pressure log attached
  • Insulation continuous

Photo evidence

  • Pressure gauge at start and end2 required

Work cannot be covered up until this hold point is inspected and accepted.

3

Starts after: Pipework and pressure test

Progress

40%

Checklist

  • High-temperature alarm tested
  • Door alarm tested
  • Setpoints match the brand standard

Photo evidence

  • Controller display1 required
4

Starts after: Controls and alarms

Progress

0%

Checklist

  • Data logger downloaded
  • Pull-down time within specification
  • Validation report uploaded

Photo evidence

  • Logger graph1 required

Work cannot be covered up until this hold point is inspected and accepted.