Task templatesShopfront and glazing
SW
Shopfront and glazing
Glazing, entrance doors and external signage interface.
Shopfront & glazing4 tasks1 hold pointsUsed by 3 packages: JM008, JM031, JM051
1
No dependency — can start at mobilisation
Progress
100%
Checklist
- Opening dimensions checked against fabrication drawing
- Structural opening signed off
- Landlord approval reference recorded
Photo evidence
- Opening before install2 required
2
Starts after: Survey and template
Progress
85%
Checklist
- Frame square within 3 mm
- Perimeter seal continuous
- Threshold drainage clear
Photo evidence
- Perimeter seal3 required
3
Starts after: Frame install and weather seal
Progress
50%
Checklist
- Glass marked with the correct safety standard
- Door closer set to the access standard
- No visible scratching
Photo evidence
- Glazing units in place2 required
4
Starts after: Glazing and door adjustment
Progress
0%
Checklist
- Landlord representative present
- Inspection sheet signed
- Snags listed and dated
Photo evidence
- Completed shopfront, daylight2 required
Work cannot be covered up until this hold point is inspected and accepted.